Miskan Al Asala
13 May 2026

Al-Asalah

64%Overall▲ +2% · vs previous visit

Main video

Engineering Report

The images show ongoing progress at the Maskan Al-Asala project, with a focus on concrete structural works and external boundary walls for the residential units. The casting of main structures for most villas in the monitored area has been completed, and waterproofing works for roofs have commenced in several units.
Detected changes
Villa Rooftops95%

Appearance of waterproofing layers (in black and white) on the rooftops of several residential units compared to the previous visit.

External Perimeter Walls90%

Significant progress in the construction of perimeter walls surrounding the residential units and the definition of entrances.

General Site85%

Organization of internal road paths between residential blocks and the removal of some construction debris.

Progress reading

Although the report indicates an overall completion rate of 0%, the images reflect a different reality where the structural frameworks (shell and core) are largely complete in the photographed areas, and waterproofing and initial external finishing works have begun.

vs previous visit

Compared to the April 18 visit, we observe an increase in the number of villas with completed roof insulation, the completion of boundary walls between units in the central blocks, and an improvement in the overall site cleanliness.

Expected next milestones

Commencement of external plastering works, installation of internal mechanical and electrical systems, and completion of road infrastructure works.

Progress

0%OverallAverage item progress
0/4 completeavg ▲ +1%
Finishing Works
0%
Fences and Courtyards▲ +2%
0%
Structural Frameworknew
0%
Foundations▲ +1%
0%

Zone 1

Zone 2

Zone 3

Models

Model R1

Model R2

Model R3