Engineering Report
Detected changes
Appearance of waterproofing layers (in black and white) on the rooftops of several residential units compared to the previous visit.
Significant progress in the construction of perimeter walls surrounding the residential units and the definition of entrances.
Organization of internal road paths between residential blocks and the removal of some construction debris.
Progress reading
Although the report indicates an overall completion rate of 0%, the images reflect a different reality where the structural frameworks (shell and core) are largely complete in the photographed areas, and waterproofing and initial external finishing works have begun.
vs previous visit
Compared to the April 18 visit, we observe an increase in the number of villas with completed roof insulation, the completion of boundary walls between units in the central blocks, and an improvement in the overall site cleanliness.
Expected next milestones
Commencement of external plastering works, installation of internal mechanical and electrical systems, and completion of road infrastructure works.