Miskan Al Asala
13 May 2026

Al-Asalah

64%Overall▲ +2% · vs previous visit

Main video

Engineering Report

The current site visit shows continued progress on site works and boundary walls, with relative stability in finishing and structural works. Slight progress was observed in boundary walls and courtyards, reflecting a current focus on the infrastructure surrounding the residential units.
Detected changes
Fences and Courtyards80%

Construction of perimeter fences and courtyard preparation continues, with noticeable progress in closing the gaps between residential units.

Structural Framework92%

The concrete structures of the residential units are nearly complete, showing stability in structural status compared to the previous visit.

Finishing Works11%

There have been no significant visible changes to the exterior or interior finishing works of the residential units in the attached photos.

Progress reading

The images align with the recorded completion percentages; the structural framework (92%) appears complete, while the images reflect progress in boundary wall works (80%) through the completion of partition and perimeter walls. Meanwhile, finishing works (11%) remain in the initial stages with no significant visual changes.

vs previous visit

Compared to the previous visit, there is a slight progress in fencing and courtyard works (+2%), while the structural framework and finishing works remain visually unchanged, indicating that resources are being directed toward completing site development.

Expected next milestones

Commencement of interior and exterior finishing works for residential units, and completion of paving and site landscaping.

Progress

0%OverallAverage item progress
0/4 completeavg ▲ +1%
Finishing Works
0%
Fences and Courtyards▲ +2%
0%
Structural Frameworknew
0%
Foundations▲ +1%
0%

Zone 1

Zone 2

Zone 3