Al-Asalah
Main video
Engineering Report
Detected changes
The concrete structure of the residential units is 99% complete, with the units now standing in their final form, ready for subsequent finishing stages.
Internal and external finishing works have progressed by 8%, with units showing significant advancement in structural preparation.
Completion of fencing and courtyards has reached 95%, with perimeter walls around the units appearing complete in most locations.
Progress reading
The attached photos reflect a steady pace of work, showing the site in a well-organized state with the concrete structures of the units completed, which accounts for the 99% structural completion and 100% foundation progress.
vs previous visit
Compared to the previous site visit, there is a noticeable increase in work intensity and progress in closing the perimeter fences around the units, with a tangible 8% advancement in finishing works, indicating a shift in focus toward interior tasks.
Expected next milestones
Focusing on completing interior finishing works, site landscaping, and commencing insulation and exterior painting for the units.