Al-Asalah
Main video
Engineering Report
Detected changes
Completion of concrete structures (skeleton) for the majority of villas in the monitored blocks
Implementation of waterproofing layers (appearing in blue) on the roofs of a group of units
Demarcation and leveling of internal road paths and commencement of sidewalk curbing works
Presence of site offices, warehouses, and material stockpiles in designated areas
Progress reading
Although the officially recorded completion rate is 0%, visual evidence indicates substantial progress in the structural framework phase, having surpassed the foundation stage. This discrepancy is likely due to pending system updates or payment certificate approvals. The units appear to be in advanced stages of shell construction and the beginning of insulation works.
vs previous visit
No previous visit available for comparison
Expected next milestones
Commencement of external plastering works, internal electrical and mechanical installations, and completion of waterproofing and thermal insulation for the roofs.