Miskan Al Asala
16 Mar 2026

Al-Asalah

60%Overall

Main video

Engineering Report

The Maskan Al-Asala project site was visited on March 16, 2026, showing significant progress in the structural framework of the residential complexes. Most foundation and excavation work has been completed, with limited initial exterior finishing work underway on select ready units.
Detected changes
Structural Framework85%

The concrete structure for most residential units in the complexes is complete, with some units reaching the final stages of roof casting.

Finishing Works10%

Exterior finishing and painting works have commenced for a limited number of residential units, with waterproofing applied to some roofs.

Site Landscaping

Internal road paving and landscaping works are ongoing, with some unpaved sandy areas still present between the complexes.

Progress reading

The images align with the reported completion percentages; the structural framework (85%) reflects the density of units with completed skeletons, while the finishing rate (10%) reflects the initial work observed in some units. Foundation and excavation work (93%) appears visually complete across most parts of the site.

vs previous visit

No previous visit available for comparison

Expected next milestones

Intensifying interior and exterior finishing works, completing paving for internal roads, and commencing site landscaping.

Progress

0%OverallAverage item progress
0/4 complete
Finishing Worksnew
0%
Excavation and Backfillingnew
0%
Structural Frameworknew
0%
Foundation Worksnew
0%

Zone 1

Zone 2

Zone 3