Detected changes
The concrete structure for most residential units in the complexes is complete, with some units reaching the final stages of roof casting.
Exterior finishing and painting works have commenced for a limited number of residential units, with waterproofing applied to some roofs.
Internal road paving and landscaping works are ongoing, with some unpaved sandy areas still present between the complexes.
Progress reading
The images align with the reported completion percentages; the structural framework (85%) reflects the density of units with completed skeletons, while the finishing rate (10%) reflects the initial work observed in some units. Foundation and excavation work (93%) appears visually complete across most parts of the site.
vs previous visit
No previous visit available for comparison
Expected next milestones
Intensifying interior and exterior finishing works, completing paving for internal roads, and commencing site landscaping.