Miskan Al Asala
16 Mar 2026

Al-Asalah

60%OverallFirst visit — no previous comparison.

Main video

Engineering Report

Significant progress has been observed in the construction works of the Maskan Al-Asala project, with most residential villas reaching the completed concrete structure (shell) stage. The images show the completion of roof casting and exterior walls for a large number of units, alongside the commencement of waterproofing works for some roofs and initial site grading for internal roads.
Detected changes
Structural Frameworks95%

Completion of concrete structures (skeleton) for the majority of villas in the monitored blocks

Rooftops90%

Implementation of waterproofing layers (appearing in blue) on the roofs of a group of units

Infrastructure and Roads85%

Demarcation and leveling of internal road paths and commencement of sidewalk curbing works

General Site80%

Presence of site offices, warehouses, and material stockpiles in designated areas

Progress reading

Although the officially recorded completion rate is 0%, visual evidence indicates substantial progress in the structural framework phase, having surpassed the foundation stage. This discrepancy is likely due to pending system updates or payment certificate approvals. The units appear to be in advanced stages of shell construction and the beginning of insulation works.

vs previous visit

No previous visit available for comparison

Expected next milestones

Commencement of external plastering works, internal electrical and mechanical installations, and completion of waterproofing and thermal insulation for the roofs.

Progress

0%OverallAverage item progress
0/4 complete
Finishing Worksnew
0%
Excavation and Backfillingnew
0%
Structural Frameworknew
0%
Foundation Worksnew
0%

Zone 1

Zone 2

Zone 3

Models

Model (1)

Model (2)

Model (3)