Al-Asalah
Main video
Engineering Report
Detected changes
Concrete structural works for residential units are ongoing, with the majority of the skeletons for the visible models now complete.
Interior finishing works have commenced in select units, including the installation of suspended ceilings, electrical wiring, and base coats of paint.
Progress is being made on site landscaping and the preparation of pathways and recreational areas, alongside the ongoing construction of perimeter fencing.
Progress reading
The photos reflect consistency with the reported completion percentages, as the structural framework is 96% complete, while finishing works are in their initial stages (16%), and fencing and site development are progressing consistently at 89%.
vs previous visit
Compared to the previous visit, there is a slight increase in the pace of construction, with a noticeable improvement in site readiness and external landscaping, which accounts for the reported increase in completion percentages.
Expected next milestones
Intensification of interior and exterior finishing works, and the commencement of final paving for the site.