Miskan Al Asala
17 Aug 2026

Al-Asalah

69%Overall▲ +1% · vs previous visit

Main video

Engineering Report

The current site visit shows slight progress across all work items, with structural works, finishes, and fencing continuing at a steady pace, with a notable focus on completing foundation and site development works.
Detected changes
Structural Framework96%

Concrete structural works for residential units are ongoing, with the majority of the skeletons for the visible models now complete.

Finishing Works16%

Interior finishing works have commenced in select units, including the installation of suspended ceilings, electrical wiring, and base coats of paint.

Site Development and Fencing

Progress is being made on site landscaping and the preparation of pathways and recreational areas, alongside the ongoing construction of perimeter fencing.

Progress reading

The photos reflect consistency with the reported completion percentages, as the structural framework is 96% complete, while finishing works are in their initial stages (16%), and fencing and site development are progressing consistently at 89%.

vs previous visit

Compared to the previous visit, there is a slight increase in the pace of construction, with a noticeable improvement in site readiness and external landscaping, which accounts for the reported increase in completion percentages.

Expected next milestones

Intensification of interior and exterior finishing works, and the commencement of final paving for the site.

Progress

0%OverallAverage item progress
0/4 completeavg ▲ +1%
Finishing Works▲ +1%
0%
Fences and Yards▲ +1%
0%
Structural Framework▲ +1%
0%
Foundations▲ +2%
0%