Engineering Report
Detected changes
Completion of slab and column pouring for most residential villas, with concrete structures reaching final form across most project sectors.
Clear progress in the construction of external boundary walls between residential units and the completion of exterior blockwork.
Commencement of interior plastering works and the installation of HVAC, electrical networks, and suspended ceilings in selected models.
Ongoing leveling of internal roads and preparation of pathways, with the features of gardens, open areas, and shades beginning to take shape.
Progress reading
The visual evidence aligns with the reported completion rates; the finished concrete structures reflect the 96% milestone, while the boundary wall works show substantial progress nearing 90%. The slight increase in finishing works (1%) is visible in the photos of interior rough-ins and ceiling installations.
vs previous visit
Compared to the previous site visit photos, there is a noticeable completion of structural framing for villas that were previously under construction, an increase in the length of boundary walls, and progress in the grading and leveling of roads surrounding the residential blocks.
Expected next milestones
Completion of the remaining structural concrete pouring, expansion of external plastering and painting works, and the commencement of internal road paving.