Miskan Al Asayel
21 Jun 2026

Al-Fursan

86%Overall▲ +2% · vs previous visit

Main video

Engineering Report

The Maskan Al-Asayel project has seen steady progress in both exterior and interior finishing works, with the structural framework and boundary walls now fully complete. The images demonstrate ongoing work on site landscaping and final finishes for the residential units.
Detected changes
Finishing Works62%

Exterior finishing works for residential units and surface installations are ongoing, with significant progress made on painting and facade work.

Site Development

Boundary walls and courtyard works are complete, with ongoing leveling and preparation of external pathways.

Progress reading

The images reflect a 2% increase in finishing works, which aligns with visual observations of progress on the facades and final unit interiors. The structural framework and boundary walls are 100% complete, as shown in the images.

vs previous visit

Compared to the previous visit, the site appears more organized with the perimeter fencing completed, and there is notable progress in the exterior finishing works of the residential units.

Expected next milestones

Completion of final interior finishing works, commencement of final road paving, and landscaping of green areas.

Progress

0%OverallAverage item progress
3/4 completeavg ▲ +2%
Finishing Works▲ +2%
0%
Fences and Courtyardsnew
0%
Structural Frameworknew
0%
Foundationsnew
0%