Al-Fursan
Main video
Engineering Report
Detected changes
Completion of exterior painting and installation of windows and doors for a large number of villas, with synthetic turf appearing on the roofs of some units as part of the landscaping works.
Ongoing grading of internal roads between residential blocks, with heavy machinery working on soil leveling and preparing infrastructure pathways.
Completion of concrete perimeter walls surrounding the residential units and installation of iron gates for certain models.
Execution of plastering, primary painting, and installation of electrical boxes and flooring in units currently under finishing.
Progress reading
The images align with the recorded progress in finishing works (+2%), showing a clear focus on final details such as the installation of rooftop water tanks, HVAC ducting, and insulation and tiling for the roofs.
vs previous visit
Compared to the previous visit, there is a noticeable progress in window installations and an increase in the number of units with completed rooftop landscaping using artificial turf, in addition to advancements in paving the roads surrounding the central blocks.
Expected next milestones
Completion of internal road asphalt works, street lighting, and final finishing (final coat of paint, sanitary fixtures, and electrical installations) for the remaining units.