Miskan Al Asayel
19 Apr 2026

Al-Fursan

83%Overall▲ +4% · vs previous visit

Main video

Engineering Report

Current photos of the Maskan Al-Asayel project show significant progress in exterior finishing works and general site landscaping. Concrete structures for most villas have been completed, with clear advancement in external plastering and primary painting, alongside the installation of overhead water tanks and the preparation of internal roads.
Detected changes
Villa Facades95%

Completion of external plastering and painting across extensive sectors compared to the structural shells seen in the previous visit

Rooftops90%

Installation of overhead water tanks in most residential units

Infrastructure and Roads85%

Grading of internal roads and laying of asphalt base layers in several pathways

Progress reading

Although the recorded percentage is 0%, the visual evidence indicates substantial completion of the structural phase and the actual commencement of the exterior finishing stage. The radical transformation between previous photos (showing grey structures) and current photos (showing colored and finished facades) confirms intensive construction activity.

vs previous visit

The visual difference is vast; previous images showed the project only at the structural skeleton stage, whereas current photos display a complete transition to the plastering and exterior painting phase, along with the installation of rooftop systems and a noticeable improvement in overall site organization.

Expected next milestones

Completion of final painting works, installation of exterior windows and doors, commencement of final paving and lighting, and landscaping of green spaces.

Progress

0%OverallAverage item progress
2/3 completeavg ▲ +1%
Structural Framework
0%
Fences and Courtyards
0%
Finishing Works▲ +3%
0%

Site (360)

3D View