Miskan Al Asayel
19 Apr 2026

Al-Fursan

83%Overall▲ +4% · vs previous visit

Main video

Engineering Report

The current site visit shows continued progress in both exterior and interior finishing works, with the structural framework and boundary walls fully completed. A tangible 3% progress in finishing works was observed, as the photos confirm the installation of solar water heaters, insulation works, and facade preparations for the residential units.
Detected changes
Finishing Works and Facades51%

Installation of solar water heaters on residential rooftops is underway, alongside progress in plastering and exterior facade painting.

Site Development and Infrastructure

Grading and leveling of open spaces between residential clusters continue, with internal roads now ready for completed units.

Progress reading

The photos align with the overall completion rate of 83%, reflecting the current focus on final finishing works (51%), while the structural framework and boundary walls (100%) appear complete and stable.

vs previous visit

Compared to the previous visit, current images show an increase in the number of solar heaters installed on the roofs and improved site cleanliness around the units, confirming that finishing work is ongoing.

Expected next milestones

Completion of interior finishing for the remaining units, commencement of landscaping works, and preparations for final handover.

Progress

0%OverallAverage item progress
2/3 completeavg ▲ +1%
Structural Framework
0%
Fences and Courtyards
0%
Finishing Works▲ +3%
0%

Site (360)

3D View

Master Plan

Drone Shots

Models

A1

A2

A3

B1

B2

C1