Al-Fursan
Main video
Engineering Report
Detected changes
Completion of external plastering and painting across extensive sectors compared to the structural shells seen in the previous visit
Installation of overhead water tanks in most residential units
Grading of internal roads and laying of asphalt base layers in several pathways
Progress reading
Although the recorded percentage is 0%, the visual evidence indicates substantial completion of the structural phase and the actual commencement of the exterior finishing stage. The radical transformation between previous photos (showing grey structures) and current photos (showing colored and finished facades) confirms intensive construction activity.
vs previous visit
The visual difference is vast; previous images showed the project only at the structural skeleton stage, whereas current photos display a complete transition to the plastering and exterior painting phase, along with the installation of rooftop systems and a noticeable improvement in overall site organization.
Expected next milestones
Completion of final painting works, installation of exterior windows and doors, commencement of final paving and lighting, and landscaping of green spaces.