Miskan Al Asayel
16 May 2026

Al-Fursan

84%Overall▲ +1% · vs previous visit

Main video

Engineering Report

Significant progress has been achieved at the Maskan Al-Asayel project, with the structural framework and perimeter fencing now 100% complete. Current efforts are focused on exterior and interior finishes, which have reached 60%, alongside the commencement of internal road paving and site landscaping.
Detected changes
Exterior Facades

Completion of plastering and exterior painting works for the majority of residential units.

Fences and Boundary Walls

Installation of iron gates and final finishing works for the villa boundary walls.

Site Development

Debris removal and commencement of earth leveling for internal roads between blocks.

Roofing

Installation of overhead water tanks and air conditioning systems in most units.

Progress reading

The visual evidence aligns with the reported completion percentages; the concrete structure is fully complete (100%), while the status of the facades and fencing reflects substantial progress in finishing works (60%), with some units currently in the final painting stages.

vs previous visit

Compared to the April visit, we observe a transition from the structural phase of the boundary walls to the final finishing and painting stages. Current photos also show improved site organization and a reduction in raw construction materials, indicating a shift toward advanced finishing works.

Expected next milestones

Completion of paving and lighting for internal roads, finishing the final paintwork for the remaining facades, and commencing the installation of utility meters and final connections.

Progress

0%OverallAverage item progress
2/3 complete
Structural Framework
0%
Fences and Yardsnew
0%
Finishing Worksnew
0%

Site (360)

3D View

Master Plan

Drone Shots

Models

A1

A2

A3

B1

B2

C1

ShareChat on WhatsApp