Engineering Report
Detected changes
Completion of plastering and exterior painting works for the majority of residential units.
Installation of iron gates and final finishing works for the villa boundary walls.
Debris removal and commencement of earth leveling for internal roads between blocks.
Installation of overhead water tanks and air conditioning systems in most units.
Progress reading
The visual evidence aligns with the reported completion percentages; the concrete structure is fully complete (100%), while the status of the facades and fencing reflects substantial progress in finishing works (60%), with some units currently in the final painting stages.
vs previous visit
Compared to the April visit, we observe a transition from the structural phase of the boundary walls to the final finishing and painting stages. Current photos also show improved site organization and a reduction in raw construction materials, indicating a shift toward advanced finishing works.
Expected next milestones
Completion of paving and lighting for internal roads, finishing the final paintwork for the remaining facades, and commencing the installation of utility meters and final connections.