Miskan Al Asayel
16 May 2026

Al-Fursan

84%Overall▲ +1% · vs previous visit

Main video

Engineering Report

Aerial and ground-level imagery show significant progress in the Maskan Al-Asayel project, with most residential villas reaching advanced stages of exterior finishing and rooftop system installation. Work is currently underway on grading internal roads, paving sidewalks, and constructing perimeter walls for the units.
Detected changes
Rooftops95%

Completion of water tank installations and solar heater systems in most units

Internal Roads90%

Commencement of paving works and laying asphalt base layers in some pathways

Facades and Fences85%

Installation of metal gates for villas and final painting works for external fences

Site Landscaping95%

Removal of construction debris and leveling of open spaces between blocks

Progress reading

Although the recorded percentage is 0%, visual evidence indicates substantial completion of structural frameworks and exterior finishes. Visible changes are concentrated in the transition from the structural shell stage to final finishing and the preparation of road infrastructure.

vs previous visit

Compared to the April 19 visit, there is a noticeable increase in the number of units with completed rooftop systems (tanks and heaters), significant progress in leveling the roads surrounding the residential blocks, and a more comprehensive installation of villa gates.

Expected next milestones

Completion of final asphalt works, installation of lighting poles, and commencement of landscaping and gardening works.

Progress

0%OverallAverage item progress
2/3 complete
Structural Framework
0%
Fences and Yardsnew
0%
Finishing Worksnew
0%

Site (360)

3D View

Master Plan