Engineering Report
Detected changes
Completion of water tank installations and solar heater systems in most units
Commencement of paving works and laying asphalt base layers in some pathways
Installation of metal gates for villas and final painting works for external fences
Removal of construction debris and leveling of open spaces between blocks
Progress reading
Although the recorded percentage is 0%, visual evidence indicates substantial completion of structural frameworks and exterior finishes. Visible changes are concentrated in the transition from the structural shell stage to final finishing and the preparation of road infrastructure.
vs previous visit
Compared to the April 19 visit, there is a noticeable increase in the number of units with completed rooftop systems (tanks and heaters), significant progress in leveling the roads surrounding the residential blocks, and a more comprehensive installation of villa gates.
Expected next milestones
Completion of final asphalt works, installation of lighting poles, and commencement of landscaping and gardening works.