Miskan Al Asayel
31 Mar 2026

Al-Fursan

79%Overall

Main video

Engineering Report

The Maskan Al-Asayel project was visited on March 31, 2026, revealing that the site is in an advanced stage of execution. The structural framework and perimeter fencing are 100% complete, while finishing works on the residential units are ongoing, with a completion rate of 48%.
Detected changes
Structural Framework100%

The concrete structure for all residential units across the entire project has been completed.

Finishing Works48%

External finishing stages vary, with some units undergoing roof waterproofing and masonry work, while facade work continues.

Site Development

Boundary walls and courtyard works are complete, with ongoing leveling and grading for roads and open spaces.

Progress reading

The images align with the reported completion percentages; the structural framework and fencing are clearly complete, while the site photos of the residential units (images 7-20) reflect the nature of the ongoing finishing works, which have reached 48%.

vs previous visit

No previous visit available for comparison

Expected next milestones

Intensifying interior and exterior finishing works, and commencing site landscaping and planting.

Progress

0%OverallAverage item progress
2/3 complete
Structural Frameworknew
0%
Fences and Courtyardsnew
0%
Finishing Worksnew
0%

Site (360)

3D View

Master Plan

Drone Shots

Models

A1

A2

A3

B1

B2

C1

ShareChat on WhatsApp