Al-Fursan
Main video
Engineering Report
Detected changes
Completion of concrete structural pouring (ground and first floors) for the majority of units in the central area
Grading and leveling of internal roads surrounding residential blocks and completion of subgrade layers
Setup of site offices and temporary warehouses, and the initial shaping of the master plan layout
تمهيد الطرق الداخلية وتركيب أعمدة الإنارة في الشوارع الرئيسية المحيطة
Progress reading
Although the recorded completion rate is 0%, the visual evidence indicates that a significant portion of the structural work has been completed. It is clearly evident that the concrete frames for a large number of units are finished, meaning the project has surpassed the foundation and footing stages across extensive areas.
vs previous visit
No previous visit available for comparison
Expected next milestones
Completion of the remaining slab casting, commencement of masonry (block) work, and initiation of basic utility installations.