31 Mar 2026
Al-Fursan
79%Overall
Main video
Engineering Report
The Maskan Al-Asayel project was visited on March 31, 2026, revealing that the site is in an advanced stage of execution. The structural framework and perimeter fencing are 100% complete, while finishing works on the residential units are ongoing, with a completion rate of 48%.
Detected changes
Structural Framework100%
The concrete structure for all residential units across the entire project has been completed.
Finishing Works48%
External finishing stages vary, with some units undergoing roof waterproofing and masonry work, while facade work continues.
Site Development
Boundary walls and courtyard works are complete, with ongoing leveling and grading for roads and open spaces.
Progress reading
The images align with the reported completion percentages; the structural framework and fencing are clearly complete, while the site photos of the residential units (images 7-20) reflect the nature of the ongoing finishing works, which have reached 48%.
vs previous visit
No previous visit available for comparison
Expected next milestones
Intensifying interior and exterior finishing works, and commencing site landscaping and planting.
Progress
0%OverallAverage item progress
2/3 complete
Structural Frameworknew
0%
100% · newvs previous visit
Fences and Courtyardsnew
0%
100% · newvs previous visit
Finishing Worksnew
0%
48% · newvs previous visit