Miskan Al Asayel
31 Mar 2026

Al-Fursan

79%OverallFirst visit — no previous comparison.

Main video

Engineering Report

Significant progress has been observed in the construction of the Maskan Al-Asayel project, with current work focused on the structural framing (skeleton) phase for a large number of residential units. The images show the completion of structural frames for several blocks, while work continues on the slabs and columns for the remaining units, alongside the leveling of the project's internal road network.
Detected changes
Structural Framework (Villas)100%

Completion of concrete structural pouring (ground and first floors) for the majority of units in the central area

Infrastructure and Roads100%

Grading and leveling of internal roads surrounding residential blocks and completion of subgrade layers

General Site85%

Setup of site offices and temporary warehouses, and the initial shaping of the master plan layout

البنية التحتية90%

تمهيد الطرق الداخلية وتركيب أعمدة الإنارة في الشوارع الرئيسية المحيطة

Progress reading

Although the recorded completion rate is 0%, the visual evidence indicates that a significant portion of the structural work has been completed. It is clearly evident that the concrete frames for a large number of units are finished, meaning the project has surpassed the foundation and footing stages across extensive areas.

vs previous visit

No previous visit available for comparison

Expected next milestones

Completion of the remaining slab casting, commencement of masonry (block) work, and initiation of basic utility installations.

Progress

0%OverallAverage item progress
2/3 complete
Structural Frameworknew
0%
Fences and Courtyardsnew
0%
Finishing Worksnew
0%