Miskan Al Sadan
9 Aug 2026

Al-Sadan

67%Overall▲ +4% · vs previous visit

Main video

Engineering Report

Significant progress was achieved in the Maskan Al-Sadan project during July, with the overall completion rate rising to 67%. Work focused primarily on interior finishing and exterior facades, alongside an accelerated pace in constructing the perimeter walls for the residential units, while maintaining 100% completion of the structural framework and foundations.
Detected changes
Finishing Works95%

Continuation of external plastering and primary painting for a large number of villas, alongside the commencement of grid ceiling installations and internal HVAC and electrical wiring in advanced units.

Fences and Yards90%

Clear progress in the construction of boundary walls between residential units and external annexes, with the visual layout of the villas' external divisions nearing completion.

Exterior Facades95%

Completion of external cladding for extensive sectors of the project, noting varying stages of exterior finishing between villas ready for painting and those still in the plastering phase.

General Site85%

Ongoing grading of internal roads between residential blocks, with heavy machinery active in leveling vacant land within the project boundaries.

Progress reading

The increase in finishing rates (+4%) is consistent with interior photos showing the installation of ceiling frameworks and service fixtures. Furthermore, the rise in perimeter wall completion (+5%) reflects the finished construction of external walls for several units that appeared as separate concrete blocks during the previous visit.

vs previous visit

Compared to the previous site visit photos, a significant number of villas have progressed from the structural shell stage to the plastering and white painting stage. Additionally, the gaps between villas have begun to decrease due to the construction of boundary walls that were either absent or in their early stages in the July photos.

Expected next milestones

Completion of final exterior facade painting, commencement of window and door installations, and ongoing progress on road and sidewalk infrastructure works.

Progress

0%OverallAverage item progress
2/4 completeavg ▲ +2%
Finishing Works▲ +4%
0%
Fences and Yards▲ +5%
0%
Structural Framework
0%
Foundations
0%

Site (360)

3D

Master Plan

Drone Shots

Models

J1

360

J2

360