Engineering Report
Detected changes
Continuation of internal electrical and mechanical installations, with piping visible in ceilings and walls, and the commencement of internal plastering for several units.
Progress in the construction of external boundary walls between residential units using cement blocks, with entrances and courtyards becoming more clearly defined.
Execution of external plastering (rendering) for a number of residential blocks, and the installation of metal scaffolding to complete facade works.
Leveling of internal roads between residential blocks and the staging of construction materials (blocks and pipes) in work areas to ensure continuity of execution.
Progress reading
The visual evidence aligns with the reported completion rates; the 4% increase in finishing works is evident through the density of internal installations shown in close-up photos. Furthermore, progress in boundary wall construction accounts for the 5% rise in that category, while the structural framework remains steady at 100% following the completion of all concrete elements.
vs previous visit
Compared to the July images, we observe a transition from the structural skeleton phase to the closing of openings and construction of perimeter walls, with a clear increase in the number of units where exterior plastering and ceiling service installations have commenced.
Expected next milestones
Completion of interior and exterior plastering works, commencement of tiling works, and ongoing implementation of road and sidewalk infrastructure.