Miskan Al Sadan
9 Aug 2026

Al-Sadan

67%Overall▲ +4% · vs previous visit

Main video

Engineering Report

Significant progress was observed at the Maskan Al-Sadan project during the August 2026 visit, with work primarily focused on the interior finishing phase and external boundary walls. The structural framework and foundations for all units have been fully completed, while work continues on service installations and external plastering for certain sectors.
Detected changes
Finishing Works95%

Continuation of internal electrical and mechanical installations, with piping visible in ceilings and walls, and the commencement of internal plastering for several units.

Fences and Courtyards90%

Progress in the construction of external boundary walls between residential units using cement blocks, with entrances and courtyards becoming more clearly defined.

Exterior Facades92%

Execution of external plastering (rendering) for a number of residential blocks, and the installation of metal scaffolding to complete facade works.

General Site95%

Leveling of internal roads between residential blocks and the staging of construction materials (blocks and pipes) in work areas to ensure continuity of execution.

Progress reading

The visual evidence aligns with the reported completion rates; the 4% increase in finishing works is evident through the density of internal installations shown in close-up photos. Furthermore, progress in boundary wall construction accounts for the 5% rise in that category, while the structural framework remains steady at 100% following the completion of all concrete elements.

vs previous visit

Compared to the July images, we observe a transition from the structural skeleton phase to the closing of openings and construction of perimeter walls, with a clear increase in the number of units where exterior plastering and ceiling service installations have commenced.

Expected next milestones

Completion of interior and exterior plastering works, commencement of tiling works, and ongoing implementation of road and sidewalk infrastructure.

Progress

0%OverallAverage item progress
2/4 completeavg ▲ +2%
Finishing Works▲ +4%
0%
Fences and Yards▲ +5%
0%
Structural Framework
0%
Foundations
0%

Site (360)

3D

Master Plan

Drone Shots

Models

J1

360

J2

360

ShareChat on WhatsApp