9 Aug 2026

Al-Sadan

67%Overall▲ +4% · vs previous visit

Main video

Engineering Report

The project has witnessed significant progress in finishing works and site development, with the structural framework and foundations fully completed at 100%. Current efforts are focused on finalizing interior and exterior finishes, as well as developing boundary walls and courtyards.
Detected changes
Finishing Works29%

Interior and exterior finishing works are ongoing, with electrical and plumbing installations underway in select units and surface preparation in progress.

Site Development and Fencing

Progress is being made on site infrastructure, including landscaping and the installation of perimeter fencing around the residential units.

Structural Framework100%

The structural framework for all units is fully complete, with no further structural construction required.

Progress reading

The images reflect a 4% increase in finishing works and a 5% increase in boundary walls and courtyards, which aligns with visual observations showing intensified work on interior finishes and the preparation of the units' surroundings.

vs previous visit

Compared to the previous visit, there is a clear increase in the pace of finishing works and site development, while the concrete structures remain unchanged as expected, given their completion.

Expected next milestones

Completion of final finishing works, commencement of painting, final electrical and plumbing installations, and intensification of site landscaping works.

Progress

0%OverallAverage item progress
2/4 completeavg ▲ +2%
Finishing Works▲ +4%
0%
Fences and Yards▲ +5%
0%
Structural Framework
0%
Foundations
0%

Site (360)