Engineering Report
Detected changes
Interior and exterior finishing works are ongoing, with electrical and plumbing installations underway in select units and surface preparation in progress.
Progress is being made on site infrastructure, including landscaping and the installation of perimeter fencing around the residential units.
The structural framework for all units is fully complete, with no further structural construction required.
Progress reading
The images reflect a 4% increase in finishing works and a 5% increase in boundary walls and courtyards, which aligns with visual observations showing intensified work on interior finishes and the preparation of the units' surroundings.
vs previous visit
Compared to the previous visit, there is a clear increase in the pace of finishing works and site development, while the concrete structures remain unchanged as expected, given their completion.
Expected next milestones
Completion of final finishing works, commencement of painting, final electrical and plumbing installations, and intensification of site landscaping works.