Engineering Report
Detected changes
Plastering and exterior facade finishing works are ongoing, with some units now displaying their final colors.
Significant progress in the construction of unit fences and courtyard preparation, contributing to the jump in completion percentage.
The structural framework for all residential units is complete, with no new structural works underway.
Progress reading
The images reflect alignment with the updated completion percentages, showing a field focus on boundary walls (17% increase) and finishing works (3% increase), while structural works remain stable at 100%.
vs previous visit
Compared to the previous visit, there is clear progress in closing the gaps between units through the construction of fences and landscaping of courtyards, along with improvements in the appearance of the exterior facades.
Expected next milestones
Completion of final finishing works (painting, flooring, and electrical installations) and general site landscaping.