Miskan Al Ghuroob
29 Mar 2026

Al-Ghuroob

56%Overall

Main video

Engineering Report

The Maskan Al-Ghoroub project site was visited on March 29, 2026, revealing that the project is in advanced stages of execution. Excavation, backfilling, and foundation works are fully complete, with the structural framework reaching 99% completion, while finishing works are ongoing at 18%.
Detected changes
Structural Framework99%

The concrete structure for most residential units is complete, with brickwork construction ongoing in certain sections.

Finishing Works18%

Initial finishing works have commenced in some units, with construction materials and equipment visible on-site.

Site Development

Excavation and backfilling works are complete, along with the preparation of internal roads and areas surrounding the units.

Progress reading

The visual status in the photos aligns with the reported completion percentages; the structural framework appears complete in most areas (99%), while the field images reflect the commencement of finishing works (18%), which are currently concentrated in the structurally completed units.

vs previous visit

No previous visit available for comparison

Expected next milestones

Intensifying interior and exterior finishing works, commencing roof waterproofing, and initiating final electrical and mechanical installations.

Progress

0%OverallAverage item progress
2/4 complete
Finishing Worksnew
0%
Excavation and Backfillingnew
0%
Structural Frameworknew
0%
Foundationsnew
0%