Engineering Report
Detected changes
Completion of concrete structures (skeleton) for the majority of units, with some units reaching the upper roof casting stage.
Grading and leveling of internal road paths between residential blocks.
Appearance of fully planned and illuminated parking areas in the northeastern part of the site.
Commencement of external wall masonry (blockwork) in several residential units.
Progress reading
Although the previously recorded completion rate was 0%, visual evidence indicates substantial progress in the structural (shell and core) phase, exceeding 40% of the total structural works for the monitored stage, with buildings clearly visible across several blocks.
vs previous visit
No previous visit available for comparison
Expected next milestones
Completion of remaining ceiling slab casting; intensive commencement of plastering works and initial electrical and mechanical installations.