Al-Ghuroob
Main video
Engineering Report
Detected changes
The concrete structure for most residential units is complete, with brickwork construction ongoing in certain sections.
Initial finishing works have commenced in some units, with construction materials and equipment visible on-site.
Excavation and backfilling works are complete, along with the preparation of internal roads and areas surrounding the units.
Progress reading
The visual status in the photos aligns with the reported completion percentages; the structural framework appears complete in most areas (99%), while the field images reflect the commencement of finishing works (18%), which are currently concentrated in the structurally completed units.
vs previous visit
No previous visit available for comparison
Expected next milestones
Intensifying interior and exterior finishing works, commencing roof waterproofing, and initiating final electrical and mechanical installations.