Al-Ghuroob
Main video
Engineering Report
Detected changes
The concrete structure for all residential units is 100% complete.
Progress in interior finishing works (electrical and plumbing installations) and surface preparation for unit interiors.
Commencement of site grading and marking of boundary lines and external courtyards.
Progress reading
The photos align with the reported completion percentages, clearly showing the finished structural framework. There is a 2% progress in finishing works, currently focused on internal installations, and the perimeter fencing and courtyard features have begun to take shape at a 7% completion rate.
vs previous visit
Compared to the previous visit, the remaining structural gap has been closed (1%), with a noticeable acceleration in interior finishing works and the commencement of boundary wall and courtyard construction, which were not visible during the previous visit.
Expected next milestones
Intensification of interior finishing works (plastering and painting), commencement of roof waterproofing, and completion of the boundary walls surrounding the units.