Miskan Al Ghuroob
15 Apr 2026

Al-Ghuroob

58%Overall-21% · vs previous visit

Main video

Engineering Report

The report indicates ongoing progress at the Maskan Al-Ghurub project, with a focus on completing the structural frameworks of the residential units. The project is currently in an advanced stage of structural shell construction, with most villas showing completed concrete frames while masonry work (blockwork) continues for other units.
Detected changes
Structural Framework95%

Completion of concrete pouring for slabs and columns for the majority of residential units across the site.

Masonry Works90%

Ongoing construction of exterior and interior walls using cement blocks in several residential blocks.

General Site85%

Grading of internal roads between residential blocks and the emergence of sidewalk features in certain areas.

Progress reading

Although the recorded percentages indicate 0%, the visual evidence confirms significant progress in the structural framework and foundations that far exceeds this figure, as concrete structures are already standing across most parts of the project.

vs previous visit

Compared to the previous visit photos, a slight progress is noted in the masonry (blockwork) for some units, along with improved organization and cleaning of the general site, while the previously completed structural frameworks remain stable.

Expected next milestones

Commencement of external plastering works, installation of preliminary electrical and mechanical systems, and the start of construction for the units' perimeter walls.

Progress

0%OverallAverage item progress
2/4 completeavg ▲ +1%
Finishing Works▲ +2%
0%
Fences and Yardsnew
0%
Structural Framework▲ +1%
0%
Foundations
0%

Site (360)

3D

General Site Plan

Drone Photos

Models

M1

M2

M4