Miskan Al Ghuroob
15 Apr 2026

Al-Ghuroob

58%Overall▲ +2% · vs previous visit

Main video

Engineering Report

The current site visit shows significant progress in interior and exterior finishing works, with the structural framework for all residential units completed and landscaping and perimeter fencing works now underway.
Detected changes
Structural Framework100%

The concrete structure for all residential units is 100% complete.

Finishing Works20%

Progress in interior finishing works (electrical and plumbing installations) and surface preparation for unit interiors.

Site Development and Fencing

Commencement of site grading and marking of boundary lines and external courtyards.

Progress reading

The photos align with the reported completion percentages, clearly showing the finished structural framework. There is a 2% progress in finishing works, currently focused on internal installations, and the perimeter fencing and courtyard features have begun to take shape at a 7% completion rate.

vs previous visit

Compared to the previous visit, the remaining structural gap has been closed (1%), with a noticeable acceleration in interior finishing works and the commencement of boundary wall and courtyard construction, which were not visible during the previous visit.

Expected next milestones

Intensification of interior finishing works (plastering and painting), commencement of roof waterproofing, and completion of the boundary walls surrounding the units.

Progress

0%OverallAverage item progress
2/4 completeavg ▲ +1%
Finishing Works▲ +2%
0%
Fences and Yardsnew
0%
Structural Framework▲ +1%
0%