Miskan Al Ghuroob
16 Sept 2026

Al-Ghuroob

74%Overall▲ +3% · vs previous visit

Main video

Engineering Report

The Maskan Al-Ghoroub project has seen significant progress in finishing and fencing works between August 19 and September 16, 2026, with completion rates rising to 41% for finishes and 30% for fencing, while structural and infrastructure works remain fully complete.
Detected changes
Finishing Works95%

Significant progress in exterior plastering and interior finishing for residential units, with some units showing initial paint coats.

Fences and Courtyards90%

Ongoing construction of perimeter boundary walls and preparation of courtyard pathways.

Structural Framework100%

The structural framework for all residential units is fully complete, with no major changes in this scope.

Site Development85%

Improved site organization, accumulation of construction materials, and preparation of internal roads.

Progress reading

The images reflect an 11% increase in finishing and fencing works, which visually aligns with the labor density and the progress of plastering and perimeter fencing around the units compared to the previous site visit.

vs previous visit

Compared to the previous visit, the current images show clear progress in facade plastering, the emergence of final finishing details, and an increase in the length of completed perimeter walls around the units.

Expected next milestones

Completion of interior finishing works (electrical and plumbing), commencement of roof waterproofing, and intensification of site and courtyard landscaping.

Progress

0%OverallAverage item progress
3/5 completeavg ▲ +4%
Finishing Works▲ +11%
0%
Fences and Courtyards▲ +11%
0%
Structural Framework
0%
Foundations
0%
Excavation and Backfilling
0%

3D

Master Plan

Drone Photos

Models

M1

360

M2

360

M4

360

M5

360