Al-Ghuroob
Main video
Engineering Report
Detected changes
A noticeable increase in plastering and exterior finishing works for residential units, with some units showing initial paint coats.
Progress in villa fencing and courtyard preparation, with ongoing leveling and grading works in the surrounding areas.
Continued internal road paving and site landscaping, with improved site cleanliness and organized storage of construction materials.
Progress reading
The images reflect an 11% increase in finishing works and an 11% increase in fencing, which aligns visually with the density of labor and equipment observed on-site, as work has shifted from the completed structural framework to an intensive focus on exterior aesthetics and boundary walls.
vs previous visit
Compared to the previous visit, the current images show clear progress in facade enclosure and plastering works, in addition to the expansion of boundary wall construction to cover larger sections of the site, enhancing the readiness of the units.
Expected next milestones
Completion of exterior painting, commencement of final road paving, and intensification of interior finishing works for the residential units.