Al-Ghuroob
Main video
Engineering Report
Detected changes
Significant progress in exterior plastering and interior finishing for residential units, with some units showing initial paint coats.
Ongoing construction of perimeter boundary walls and preparation of courtyard pathways.
The structural framework for all residential units is fully complete, with no major changes in this scope.
Improved site organization, accumulation of construction materials, and preparation of internal roads.
Progress reading
The images reflect an 11% increase in finishing and fencing works, which visually aligns with the labor density and the progress of plastering and perimeter fencing around the units compared to the previous site visit.
vs previous visit
Compared to the previous visit, the current images show clear progress in facade plastering, the emergence of final finishing details, and an increase in the length of completed perimeter walls around the units.
Expected next milestones
Completion of interior finishing works (electrical and plumbing), commencement of roof waterproofing, and intensification of site and courtyard landscaping.