Miskan Al Asala
28 Jun 2026

Al-Asalah

66%Overall▲ +2% · vs previous visit

Main video

Engineering Report

The current site visit shows significant progress across all work items, with the overall completion rate reaching 66%. Efforts have primarily focused on completing boundary walls and courtyards, while work continues steadily on the structural framework and initial finishing stages.
Detected changes
Structural Framework95%

Completion of the concrete structure for most residential units, with ongoing insulation and roofing works.

Boundary Walls and Courtyards

Significant progress in the construction of villa boundary walls and the demarcation of external courtyards.

Site Development

Improved site organization and preparation of pathways between residential units.

Progress reading

The photos reflect continuous development in the structural framework (reaching 95%), with units now structurally complete. Progress on boundary walls (88%) is also clearly visible through the completion of most perimeter walls, accounting for an 8% increase since the previous visit.

vs previous visit

Compared to the previous visit, there is a clear increase in the intensity of fencing and boundary wall construction, with the structural framework nearing completion and the initial stages of exterior finishing becoming visible in some units.

Expected next milestones

Focusing on intensifying interior and exterior finishing works, and commencing site paving and landscaping.

Progress

0%OverallAverage item progress
0/4 completeavg ▲ +4%
Finishing Works▲ +4%
0%
Fences and Courtyards▲ +8%
0%
Structural Framework▲ +3%
0%
Foundations▲ +1%
0%

Zone 1

Zone 2

Zone 3

Models

Model R1

Model R2