Al-Asalah
Main video
Engineering Report
Detected changes
Completion of concrete pouring for ceilings and walls in most residential units, with minor work remaining on the upper parapets.
Significant progress in constructing residential unit fences and defining entrances, with fences structurally complete in most sectors.
Grading of internal roads between residential blocks and clear service paths, with ongoing earthwork leveling.
Commencement of external plastering and installation of initial utility extensions in selected units, currently in the early stages.
Progress reading
The photographs align with the reported completion rates; the finished concrete structures reflect the 95% milestone, while the intensified work on the perimeter walls (88%) is clearly visible as a key element of this phase. The progress in finishing works (+4%) is beginning to manifest visually on several facades.
vs previous visit
Compared to the previous visit's photos, it is noted that structural gaps in the upper ceilings of several villas have been closed, and there is a significant transformation in the overall site layout from scattered structures into defined residential blocks with their own boundary walls.
Expected next milestones
Focusing on finishing external plastering works, commencing internal mechanical and electrical system installations, and completing the paving of internal roads.