Miskan Al Asala
28 Jun 2026

Al-Asalah

66%Overall▲ +2% · vs previous visit

Main video

Engineering Report

Significant progress has been achieved in the Maskan Al-Asala project, with the overall completion rate reaching 66%. Work has primarily focused on completing the structural framework, which is nearing completion at 95%, alongside accelerated work on the perimeter walls for the residential units and the commencement of initial finishing stages.
Detected changes
Structural Framework95%

Completion of concrete pouring for slabs and columns for most residential villas, with concrete structures fully visible across most sectors.

Fences and Courtyards90%

Significant progress in the construction of external boundary walls between residential units, with courtyard perimeter walls appearing complete across large areas.

Finishing Works75%

Commencement of external plastering for some units and the appearance of initial utility installations, with construction materials and equipment present on-site.

Site Layout and Infrastructure85%

Grading of internal roads between residential blocks and clear definition of traffic paths, with ongoing earthwork and leveling.

Progress reading

The visible progress aligns with the recorded increases in the structural framework (+3%) and perimeter walls (+8%). The rise in the wall completion percentage is the most visually prominent, marking the definition of privacy for each villa, while the 15% progress in finishing reflects the start of work on the exterior facades.

vs previous visit

Compared to the previous visit's photos, a shift in focus is observed from casting major structural elements to closing voids and constructing perimeter walls. Additionally, the general site appears more organized with more clearly defined road paths.

Expected next milestones

Completion of external plastering works, commencement of internal mechanical and electrical system installations, and initiation of internal road paving works.

Progress

0%OverallAverage item progress
0/4 completeavg ▲ +4%
Finishing Works▲ +4%
0%
Fences and Courtyards▲ +8%
0%
Structural Framework▲ +3%
0%
Foundations▲ +1%
0%

Zone 1

Zone 2

Zone 3

Models

Model R1

Model R2