Al-Asalah
Main video
Engineering Report
Detected changes
Completion of concrete pouring for slabs and columns for most residential villas, with concrete structures fully visible across most sectors.
Significant progress in the construction of external boundary walls between residential units, with courtyard perimeter walls appearing complete across large areas.
Commencement of external plastering for some units and the appearance of initial utility installations, with construction materials and equipment present on-site.
Grading of internal roads between residential blocks and clear definition of traffic paths, with ongoing earthwork and leveling.
Progress reading
The visible progress aligns with the recorded increases in the structural framework (+3%) and perimeter walls (+8%). The rise in the wall completion percentage is the most visually prominent, marking the definition of privacy for each villa, while the 15% progress in finishing reflects the start of work on the exterior facades.
vs previous visit
Compared to the previous visit's photos, a shift in focus is observed from casting major structural elements to closing voids and constructing perimeter walls. Additionally, the general site appears more organized with more clearly defined road paths.
Expected next milestones
Completion of external plastering works, commencement of internal mechanical and electrical system installations, and initiation of internal road paving works.