Engineering Report
Detected changes
Completion of concrete pouring for most residential villas, with the structure reaching 95% completion, as slabs and columns are now finalized across most sectors.
External fencing for the villas has reached advanced stages at 88%, with perimeter walls now clearly surrounding the units in a uniform manner.
Ongoing leveling of internal roads and preparation of pedestrian walkways and public landscaping, which are now beginning to take clear shape.
Commencement of external plastering and primary painting works on a limited number of units, accounting for the recorded 15% progress.
Progress reading
The site photos align with the reported completion rates, as construction efforts are currently focused on finalizing the structures (95%) and perimeter walls (88%). The slight increase in foundation work (+2%) reflects the completion of the remaining footings in the project's peripheral areas.
vs previous visit
Compared to the previous site visit photos, there is a noticeable increase in the density of completed perimeter walls around the residential blocks, along with improvements in general site organization and the preparation of internal road paths.
Expected next milestones
The expected focus for the upcoming period will be on intensifying interior and exterior finishing works (plastering and painting) and connecting the infrastructure networks.