Al-Asalah
Main video
Engineering Report
Detected changes
Concrete structures for most residential units are complete, with waterproofing works for the roofs currently underway.
Waterproofing has commenced on the roofs of select units, while interior finishing works continue at a slow pace.
Site grading and leveling are ongoing, alongside the demarcation of road paths and perimeter fencing for the units.
Progress reading
Completion rates reflect stability in the structural framework (91%) and foundations (93%), while finishing works show a marginal increase of only 1%. This aligns with site imagery, which indicates a focus on concrete structures and waterproofing rather than final finishes.
vs previous visit
Compared to the previous visit, there are no significant changes to the structural framework as it has reached an advanced stage, while there is a slight improvement in roof waterproofing and general site preparation.
Expected next milestones
Intensification of interior and exterior finishing works, and the commencement of utility installations for the general site.