Miskan Al Asala
18 Apr 2026

Al-Asalah

62%Overall▲ +2% · vs previous visit

Main video

Engineering Report

The current site visit shows ongoing structural and fencing works, with slight progress in finishing works. Most concrete structures for the residential units are complete, while roof waterproofing and site preparation are currently underway.
Detected changes
Structural Framework91%

Concrete structures for most residential units are complete, with waterproofing works for the roofs currently underway.

Finishing Works11%

Waterproofing has commenced on the roofs of select units, while interior finishing works continue at a slow pace.

Site Development and Fencing

Site grading and leveling are ongoing, alongside the demarcation of road paths and perimeter fencing for the units.

Progress reading

Completion rates reflect stability in the structural framework (91%) and foundations (93%), while finishing works show a marginal increase of only 1%. This aligns with site imagery, which indicates a focus on concrete structures and waterproofing rather than final finishes.

vs previous visit

Compared to the previous visit, there are no significant changes to the structural framework as it has reached an advanced stage, while there is a slight improvement in roof waterproofing and general site preparation.

Expected next milestones

Intensification of interior and exterior finishing works, and the commencement of utility installations for the general site.

Progress

0%OverallAverage item progress
0/4 completeavg ▲ +1%
Finishing Works▲ +1%
0%
Fences and Courtyardsnew
0%
Structural Frameworknew
0%
Foundationsnew
0%

Zone 1

Zone 2

Zone 3