Al-Fursan
Main video
Engineering Report
Detected changes
External and internal finishing works are ongoing, with roof installations and final facade finishes completed for most units.
The structural framework is fully complete for all units, with no new construction works underway.
Landscaping and site development works are continuing, with boundary walls and enclosures remaining complete as observed in the previous visit.
Progress reading
The 3% increase in finishing works aligns with visual observations showing ongoing progress on the fine details of the residential units, while the structural and fencing percentages have stabilized at 100% due to their actual completion.
vs previous visit
Compared to the previous visit, there are no fundamental changes to the structural framework or fencing, while there is slight, cumulative progress in exterior finishing works and general site preparation.
Expected next milestones
Completion of final finishing works, commencement of final paving for internal roads, and site preparation for final handover.