Miskan Al Asayel
16 Aug 2026

Al-Fursan

89%Overall▲ +2% · vs previous visit

Main video

Engineering Report

Significant progress has been achieved at the Maskan Al-Asayel project, with a 3% increase in finishing works reaching 73%, while the structural framework and perimeter walls are 100% complete. Current efforts are focused on completing external facades, installing rooftop systems, and commencing paving and general site landscaping.
Detected changes
Finishing and Facade Works95%

Significant progress in exterior facade painting and the installation of rooftop water tanks and solar heaters, with ongoing interior finishing works for select units.

General Site and Infrastructure90%

Commencement of bordering and sidewalk demarcation, alongside the leveling of internal roads in preparation for paving, as landscaping and open space features begin to take shape.

Structural Framework and Perimeter Walls100%

Final completion of all reinforced concrete structures for the residential units and the external perimeter walls.

Progress reading

The visual evidence aligns with the reported completion rates; the structural framework appears fully complete, while the detailed images of rooftop and facade works reflect the ongoing progress in the finishing phase (increasing from 70% to 73%).

vs previous visit

Compared to the previous visit's photos, we observe an increase in the number of units with rooftop water systems installed, along with progress in soil leveling for internal roads and the demarcation of sidewalks, which were previously in the early stages.

Expected next milestones

Commencement of internal road asphalt works, completion of lighting installation, and finishing the final facade painting for the remaining units.

Progress

0%OverallAverage item progress
2/3 completeavg ▲ +1%
Structural Framework
0%
Fences and Yards
0%
Finishing Works▲ +3%
0%

Site (360)

3D

General Site

Drone Photos

Models

A1

A2

A3

B1

B2

C1