Miskan Al Asayel
16 Aug 2026

Al-Fursan

89%Overall▲ +2% · vs previous visit

Main video

Engineering Report

The current site visit shows a notable 3% progress in finishing works, with the structural framework and perimeter fencing remaining stable, reflecting a focus on the project's final stages.
Detected changes
Finishing Works73%

External and internal finishing works are ongoing, with roof installations and final facade finishes completed for most units.

Structural Framework100%

The structural framework is fully complete for all units, with no new construction works underway.

Site Development

Landscaping and site development works are continuing, with boundary walls and enclosures remaining complete as observed in the previous visit.

Progress reading

The 3% increase in finishing works aligns with visual observations showing ongoing progress on the fine details of the residential units, while the structural and fencing percentages have stabilized at 100% due to their actual completion.

vs previous visit

Compared to the previous visit, there are no fundamental changes to the structural framework or fencing, while there is slight, cumulative progress in exterior finishing works and general site preparation.

Expected next milestones

Completion of final finishing works, commencement of final paving for internal roads, and site preparation for final handover.

Progress

0%OverallAverage item progress
2/3 completeavg ▲ +1%
Structural Framework
0%
Fences and Yards
0%
Finishing Works▲ +3%
0%

Site (360)

3D

General Site

Drone Photos

Models

A1

A2

A3

B1

B2

C1