Engineering Report
Detected changes
Significant progress in exterior facade painting and the installation of rooftop water tanks and solar heaters, with ongoing interior finishing works for select units.
Commencement of bordering and sidewalk demarcation, alongside the leveling of internal roads in preparation for paving, as landscaping and open space features begin to take shape.
Final completion of all reinforced concrete structures for the residential units and the external perimeter walls.
Progress reading
The visual evidence aligns with the reported completion rates; the structural framework appears fully complete, while the detailed images of rooftop and facade works reflect the ongoing progress in the finishing phase (increasing from 70% to 73%).
vs previous visit
Compared to the previous visit's photos, we observe an increase in the number of units with rooftop water systems installed, along with progress in soil leveling for internal roads and the demarcation of sidewalks, which were previously in the early stages.
Expected next milestones
Commencement of internal road asphalt works, completion of lighting installation, and finishing the final facade painting for the remaining units.