Al-Fursan
Main video
Engineering Report
Detected changes
Significant progress has been made on the exterior facade finishes and roof preparation, with the majority of painting and final finishing works now complete.
Landscaping works continue, including internal road paving and the preparation of pathways and open spaces between residential clusters.
The structural framework, fencing, and boundary walls have been fully completed, with no further structural changes.
Progress reading
The images reflect a 9% increase in finishing works, with residential units reaching their final stages of exterior appearance and surface preparation. The 10% progress in inspection and commissioning aligns with the start of final utility and service preparation.
vs previous visit
Compared to the previous visit, the current images show greater completion in the exterior facade details and site landscaping, with work transitioning from major construction to final touches and commissioning.
Expected next milestones
Completion of testing and commissioning for all systems, final paving of the site, and the commencement of cleaning and preliminary handover.