Miskan Al Asayel
22 Oct 2026

Al-Fursan

94%Overall▲ +1% · vs previous visit

Main video

Engineering Report

The project has seen significant progress in both exterior and interior finishing works, with the structural framework and perimeter fencing now fully completed. Current efforts are focused on site landscaping, final unit finishes, and the commencement of inspection and commissioning procedures.
Detected changes
Finishing Works95%

Significant progress has been made on the exterior facade finishes and roof preparation, with the majority of painting and final finishing works now complete.

Site Development90%

Landscaping works continue, including internal road paving and the preparation of pathways and open spaces between residential clusters.

Structural Framework and Fencing100%

The structural framework, fencing, and boundary walls have been fully completed, with no further structural changes.

Progress reading

The images reflect a 9% increase in finishing works, with residential units reaching their final stages of exterior appearance and surface preparation. The 10% progress in inspection and commissioning aligns with the start of final utility and service preparation.

vs previous visit

Compared to the previous visit, the current images show greater completion in the exterior facade details and site landscaping, with work transitioning from major construction to final touches and commissioning.

Expected next milestones

Completion of testing and commissioning for all systems, final paving of the site, and the commencement of cleaning and preliminary handover.

Progress

0%OverallAverage item progress
2/4 completeavg ▲ +3%
Structural Framework
0%
Fencing and Boundary Walls
0%
Finishing Works▲ +9%
0%
Testing and Commissioningnew
0%