Engineering Report
Detected changes
Completion of painting works, installation of doors, and preparation of electrical and plumbing installations in residential units.
Continuation of landscaping and exterior facade works for structurally completed residential units.
Progress reading
The images reflect a 15% increase in finishing works compared to the previous visit, which aligns with the visual status of the units as they enter the final stages of interior preparation.
vs previous visit
Compared to the previous visit, the current images show significant progress in the interior readiness of the units, with doors installed and painting and finishing works completed, which were only in the initial stages during the last visit.
Expected next milestones
Completion of landscaping works, general site cleanup, and the commencement of preliminary handover procedures for completed units.