Al-Sadan
Main video
Engineering Report
Detected changes
100% completion of the concrete structures for the residential units, including columns, slabs, and roof parapets.
Execution of external and internal walling using cement blocks, and the commencement of external plastering for certain blocks, with initial electrical installations visible in the interior photos.
Commencement of white external painting and cladding on a group of units on the western side of the project, reflecting a 15% progress in finishing works.
Grading of internal road paths between residential blocks, with a heavy presence of concrete pouring equipment (pumps and mixers), tower cranes, and construction materials.
Progress reading
Visual observations align with the reported completion rates; the completion of the structural framework (100%) is evident across all project sectors, while the 15% allocated for finishing is concentrated on the facades of completed units, plastering, and internal masonry. Excavation and backfilling works (98%) are reflected in the leveled ground of the general site, which is ready for paving works.
vs previous visit
No previous visit available for comparison
Expected next milestones
Completion of external plastering and painting for the remaining units, and commencement of internal road paving and general site landscaping.