Miskan Al Sadan
30 Mar 2026

Al-Sadan

53%OverallFirst visit — no previous comparison.

Main video

Engineering Report

The Maskan Al-Sadan project was visited on March 30, 2026, with the overall completion rate reaching 53%. The project shows significant progress in the structural framework, which is 100% complete for most visible units, while exterior and interior finishing works have commenced in specific areas. The general site is witnessing activity in leveling internal roads with a heavy presence of construction equipment.
Detected changes
Structural Framework100%

100% completion of the concrete structures for the residential units, including columns, slabs, and roof parapets.

Masonry and Initial Finishing Works95%

Execution of external and internal walling using cement blocks, and the commencement of external plastering for certain blocks, with initial electrical installations visible in the interior photos.

External Facades100%

Commencement of white external painting and cladding on a group of units on the western side of the project, reflecting a 15% progress in finishing works.

General Site and Infrastructure90%

Grading of internal road paths between residential blocks, with a heavy presence of concrete pouring equipment (pumps and mixers), tower cranes, and construction materials.

Progress reading

Visual observations align with the reported completion rates; the completion of the structural framework (100%) is evident across all project sectors, while the 15% allocated for finishing is concentrated on the facades of completed units, plastering, and internal masonry. Excavation and backfilling works (98%) are reflected in the leveled ground of the general site, which is ready for paving works.

vs previous visit

No previous visit available for comparison

Expected next milestones

Completion of external plastering and painting for the remaining units, and commencement of internal road paving and general site landscaping.

Progress

0%OverallAverage item progress
2/4 complete
Finishing Worksnew
0%
Excavation and Backfillingnew
0%
Structural Frameworknew
0%
Foundationsnew
0%

Site (360)

3D View

Master Plan

Drone Shots

Models

J1

J2

ShareChat on WhatsApp