Al-Sadan
Main video
Engineering Report
Detected changes
Completion of column and slab casting for most residential units across the general site
Commencement of plastering and white painting works for several residential blocks in the northwestern section
Grading of internal roads between blocks and presence of concrete mixer trucks on-site
Construction of boundary walls between residential units for specific models
Progress reading
Although the officially recorded completion rate is 0%, visual evidence indicates significant progress in the structural (skeleton) phase, far exceeding the foundation stage. Hundreds of units are visible in advanced stages of structural construction and the beginning of finishing works.
vs previous visit
No previous visit available for comparison
Expected next milestones
Completion of external plastering works, commencement of window and door installations, and extension of basic utility networks within the paved roads.