Engineering Report
Detected changes
Concrete structures for all residential units in the master plan are complete, with some units now entering the exterior finishing phase (initial painting).
Brickwork and internal electrical installations have commenced in select units, while others have already received plastering or exterior paint coats.
Infrastructure works for roads and pathways are in their final stages, with heavy machinery and concrete pouring equipment currently active on-site.
Progress reading
The images align with the reported progress percentages; the structural framework is 100% complete across the entire site. Meanwhile, the limited imagery of finishing works (such as image 20) reflects the commencement of installations and interior finishes, which justifies the 15% completion rate recorded for finishing works.
vs previous visit
No previous visit available for comparison
Expected next milestones
Intensifying interior finishing works (plastering, MEP installations, flooring) and commencing site landscaping and exterior facade finishing.