Main video

Engineering Report

Extensive progress has been observed in the concrete structural works of the Maskan Al-Sadan project. Aerial and perspective imagery show the completion of structural frameworks for a large number of residential villas, with the commencement of external plastering and primary painting in specific sectors, alongside the leveling of the internal road network.
Detected changes
Structural Framework95%

Completion of column and slab casting for most residential units across the general site

Exterior Finishes85%

Commencement of plastering and white painting works for several residential blocks in the northwestern section

Infrastructure90%

Grading of internal roads between blocks and presence of concrete mixer trucks on-site

Fencing and Perimeter80%

Construction of boundary walls between residential units for specific models

Progress reading

Although the officially recorded completion rate is 0%, visual evidence indicates significant progress in the structural (skeleton) phase, far exceeding the foundation stage. Hundreds of units are visible in advanced stages of structural construction and the beginning of finishing works.

vs previous visit

No previous visit available for comparison

Expected next milestones

Completion of external plastering works, commencement of window and door installations, and extension of basic utility networks within the paved roads.