Miskan Al Sadan
30 Mar 2026

Al-Sadan

53%Overall

Main video

Engineering Report

The Maskan Al-Sadan project site was visited on March 30, 2026, revealing that construction is at an advanced stage. The structural framework is 100% complete for the majority of units, with interior and exterior finishing works currently in their initial phases.
Detected changes
Structural Framework100%

Concrete structures for all residential units in the master plan are complete, with some units now entering the exterior finishing phase (initial painting).

Finishing Works15%

Brickwork and internal electrical installations have commenced in select units, while others have already received plastering or exterior paint coats.

Site Development

Infrastructure works for roads and pathways are in their final stages, with heavy machinery and concrete pouring equipment currently active on-site.

Progress reading

The images align with the reported progress percentages; the structural framework is 100% complete across the entire site. Meanwhile, the limited imagery of finishing works (such as image 20) reflects the commencement of installations and interior finishes, which justifies the 15% completion rate recorded for finishing works.

vs previous visit

No previous visit available for comparison

Expected next milestones

Intensifying interior finishing works (plastering, MEP installations, flooring) and commencing site landscaping and exterior facade finishing.

Progress

0%OverallAverage item progress
2/4 complete
Finishing Worksnew
0%
Excavation and Backfillingnew
0%
Structural Frameworknew
0%
Foundationsnew
0%