Detected changes
The structural framework for all residential units is complete, with insulation works and final concrete roofing now visible.
Electrical installation works (conduit routing and wall chasing) have commenced within the units, while exterior plastering continues on select models.
Excavation and underground sewage piping works have expanded, alongside the ongoing construction of perimeter boundary walls.
Progress reading
The images reflect progress consistent with the reported completion percentages; the structural framework is complete (100%), while the increase in finishing works (from 18% to 22%) is reflected in the commencement of internal installations, and the increase in boundary wall progress (from 14% to 16%) is evident in the visible excavation and foundation work.
vs previous visit
Compared to the previous visit, the project has transitioned from the concrete skeleton phase to technical installations and initial finishing works, with an increase in labor and equipment density across the site.
Expected next milestones
Completion of internal plastering works, commencement of roof waterproofing installations, and intensification of infrastructure works for boundary walls and courtyards.