Miskan Al Sadan
15 Jun 2026

Al-Sadan

66%Overall▲ +9% · vs previous visit

Main video

Engineering Report

The report shows significant progress in the construction works of the Maskan Al-Sadan project. Current activities are focused on completing the concrete structures for the residential villas, with waterproofing works for roofs commencing in several units, alongside the ongoing masonry work for external walls and internal partitions.
Detected changes
Villa Rooftops95%

Implementation of waterproofing layers (blue/black) across a large number of units

Structural Frameworks90%

Completion of final roof slab pouring for the majority of villas in central areas

General Site85%

Increase in material stockpiling (bricks) and commencement of boundary wall construction between units

Internal Roads90%

Initial grading and leveling of road paths between residential blocks

Progress reading

Although the recorded overall completion rate is 0%, the photographs reflect a different reality where concrete structures have been completed for a large portion of the project, and the waterproofing and initial finishing stages have begun. This indicates a discrepancy between the administrative updates and the actual progress on-site.

vs previous visit

Compared to the May 2026 visit, we observe progress in casting the upper annex ceilings, and insulation materials are clearly visible on surfaces that were exposed concrete in the previous visit. Additionally, there is progress in the masonry (blockwork) for the facades and perimeter walls.

Expected next milestones

Completion of roof waterproofing and thermal insulation, commencement of external plastering works, and installation of initial mechanical and electrical system rough-ins.

Progress

0%OverallAverage item progress
2/4 completeavg ▲ +2%
Finishing Works▲ +4%
0%
Fences and Courtyards▲ +2%
0%
Structural Frameworknew
0%
Foundations
0%

Site (360)

3D View

Master Plan

Drone Shots

Models

J1

J2

ShareChat on WhatsApp