Miskan Al Sadan
15 Jun 2026

Al-Sadan

61%Overall▲ +4% · vs previous visit

Main video

Engineering Report

The current site visit shows significant progress in interior and exterior finishing works, with ongoing work on site preparation and boundary walls. The structural framework is fully complete, with current efforts focused on electrical and plumbing installations and architectural finishes.
Detected changes
Structural Framework100%

The structural framework for all residential units is complete, with insulation works and final concrete roofing now visible.

Finishing Works22%

Electrical installation works (conduit routing and wall chasing) have commenced within the units, while exterior plastering continues on select models.

Site Development and Fencing

Excavation and underground sewage piping works have expanded, alongside the ongoing construction of perimeter boundary walls.

Progress reading

The images reflect progress consistent with the reported completion percentages; the structural framework is complete (100%), while the increase in finishing works (from 18% to 22%) is reflected in the commencement of internal installations, and the increase in boundary wall progress (from 14% to 16%) is evident in the visible excavation and foundation work.

vs previous visit

Compared to the previous visit, the project has transitioned from the concrete skeleton phase to technical installations and initial finishing works, with an increase in labor and equipment density across the site.

Expected next milestones

Completion of internal plastering works, commencement of roof waterproofing installations, and intensification of infrastructure works for boundary walls and courtyards.

Progress

0%OverallAverage item progress
2/4 completeavg ▲ +2%
Finishing Works▲ +4%
0%
Fences and Courtyards▲ +2%
0%
Structural Frameworknew
0%
Foundations
0%

Site (360)

3D View

Master Plan

Drone Shots

Models

J1

J2

ShareChat on WhatsApp