Miskan Al Sadan
15 Jun 2026

Al-Sadan

61%Overall▲ +4% · vs previous visit

Main video

Engineering Report

Significant progress has been made on the Maskan Al-Sadan project, with the overall completion rate reaching 61%. The structural framework and foundations are 100% complete, with current efforts focused on interior and exterior finishing works, which have reached 22%, and the development of boundary walls and courtyards at 16%. Aerial and interior photographs demonstrate ongoing work on utility installations and exterior plastering.
Detected changes
Structural Framework and Masonry100%

Completion of all concrete works for all villas and commencement of cement brick masonry for internal and external partitions.

Finishing Works95%

Commencement of internal electrical and mechanical installations, along with initial plastering on some facades and surface insulation preparation.

Fencing and Site Development90%

Execution of foundations and columns for villa fences, and the start of grading internal roads between residential blocks.

Exterior Facades95%

Installation of metal scaffolding on a large number of villas to begin external plastering and painting works.

Progress reading

The visual progress aligns with the recorded increase in finishing works (+4%), as the project transitions from the structural shell phase to electromechanical installations and plastering. A slight advancement in boundary walls (+2%) is also evident through the completion of concrete pouring for sections of the courtyard walls.

vs previous visit

Compared to the May 2026 visit, we observe an increased density of external scaffolding and the initial appearance of piping and wiring installations within the rooms. Additionally, the internal road layouts have become clearly defined, whereas they were previously unpaved dirt areas.

Expected next milestones

Completion of external plastering works, commencement of window and door installations, and ongoing progress on waterproofing for roofs and bathrooms.

Progress

0%OverallAverage item progress
2/4 completeavg ▲ +2%
Finishing Works▲ +4%
0%
Fences and Courtyards▲ +2%
0%
Structural Frameworknew
0%
Foundations
0%

Site (360)

3D View

Master Plan

Drone Shots

Models

J1

J2

ShareChat on WhatsApp