Miskan Al Sadan
16 Apr 2026

Al-Sadan

55%Overall▲ +2% · vs previous visit

Main video

Engineering Report

Significant progress has been observed in the Maskan Al-Sadan project, with the structural framework 100% complete for all units. Interior and exterior finishing works are ongoing, alongside waterproofing and thermal insulation for the roofs. Additionally, construction of perimeter walls and courtyards has commenced in specific areas of the general site.
Detected changes
Structural Framework100%

Completion of all concrete elements for the residential units, including columns, slabs, and roof parapets.

Masonry and Finishing Works95%

Continuation of internal partition masonry using cement blocks, commencement of external plastering for select units, and installation of electrical and mechanical rough-ins.

Insulation and Roofing Works100%

Execution of waterproofing (bituminous membranes) and thermal insulation (blue foam) for the residential villa roofs to ensure leak protection.

General Site and Perimeter Fencing90%

Commencement of excavation and casting of concrete footings, along with blockwork for unit perimeters and external courtyards.

Progress reading

The site photos align with the reported completion rates, clearly showing the structural framework is finished. The slight increase in finishing works (1%) is reflected in the widespread insulation work and service installations within the units. The 9% progress in walls and courtyards is visually supported by the start of construction surrounding the units.

vs previous visit

Compared to the previous visit, a significant expansion in the scope of roof insulation (blue foam) is noted, along with an increase in the number of units where interior masonry and exterior boundary wall works have commenced, reinforcing the transition from the structural phase to the finishing phase.

Expected next milestones

Completion of exterior plastering works, commencement of window and door installations, and ongoing progress in internal road paving for the general site.

Progress

0%OverallAverage item progress
1/4 completeavg ▼ -28%
Finishing Works▲ +1%
0%
Fences and Courtyardsnew
0%
Structural Framework
0%
Foundations-84%
0%

Site (360)