Miskan Al Sadan
16 Apr 2026

Al-Sadan

55%Overall▲ +2% · vs previous visit

Main video

Engineering Report

The structural framework of the project is fully complete, with interior and exterior finishing works progressing at a completion rate of 16%. Minor progress has been observed in site development and fencing works.
Detected changes
Structural Framework100%

Completion of the concrete structure for all residential units, with waterproofing works for roofs underway in select models.

Finishing Works16%

Ongoing masonry (block) works and installation of electrical and mechanical service conduits within the units.

Site Development

Commencement of site grading and preparation for perimeter fencing and external courtyard pathways.

Progress reading

The images align with the reported completion rates; the structural framework is 100% complete, while interior images (13-20) reflect the progress of finishing works (16%) through masonry and utility installations.

vs previous visit

Compared to the previous visit, there are no significant changes to the structural framework, while slight progress is evident in interior finishing works and the preparation of the general site and fencing.

Expected next milestones

Intensification of interior finishing works (plastering and painting) and the commencement of broader waterproofing and thermal insulation works for the roofs.

Progress

0%OverallAverage item progress
1/4 completeavg ▼ -28%
Finishing Works▲ +1%
0%
Fences and Courtyardsnew
0%
Structural Framework
0%
Foundations▼ -84%
0%

Site (360)

3D View

Master Plan

Drone Shots

Models

J1

J2