Al-Sadan
Main video
Engineering Report
Detected changes
Completion of the concrete structure for all residential units, with waterproofing works for roofs underway in select models.
Ongoing masonry (block) works and installation of electrical and mechanical service conduits within the units.
Commencement of site grading and preparation for perimeter fencing and external courtyard pathways.
Progress reading
The images align with the reported completion rates; the structural framework is 100% complete, while interior images (13-20) reflect the progress of finishing works (16%) through masonry and utility installations.
vs previous visit
Compared to the previous visit, there are no significant changes to the structural framework, while slight progress is evident in interior finishing works and the preparation of the general site and fencing.
Expected next milestones
Intensification of interior finishing works (plastering and painting) and the commencement of broader waterproofing and thermal insulation works for the roofs.