Al-Sadan
Main video
Engineering Report
Detected changes
Completion of all concrete elements for the residential units, including columns, slabs, and roof parapets.
Continuation of internal partition masonry using cement blocks, commencement of external plastering for select units, and installation of electrical and mechanical rough-ins.
Execution of waterproofing (bituminous membranes) and thermal insulation (blue foam) for the residential villa roofs to ensure leak protection.
Commencement of excavation and casting of concrete footings, along with blockwork for unit perimeters and external courtyards.
Progress reading
The site photos align with the reported completion rates, clearly showing the structural framework is finished. The slight increase in finishing works (1%) is reflected in the widespread insulation work and service installations within the units. The 9% progress in walls and courtyards is visually supported by the start of construction surrounding the units.
vs previous visit
Compared to the previous visit, a significant expansion in the scope of roof insulation (blue foam) is noted, along with an increase in the number of units where interior masonry and exterior boundary wall works have commenced, reinforcing the transition from the structural phase to the finishing phase.
Expected next milestones
Completion of exterior plastering works, commencement of window and door installations, and ongoing progress in internal road paving for the general site.