Al-Sadan
Main video
Engineering Report
Detected changes
Significant progress in plastering and exterior painting for select units, with ongoing internal electrical and mechanical installations.
Continued site grading and preparation of exterior fencing for the residential units.
Progress reading
The images reflect a 4% increase in finishing works and a 6% increase in fencing, which aligns with visual observations of accelerated plastering, exterior finishing, and site preparation around the units.
vs previous visit
Compared to the previous visit, the images show an increase in the number of units where exterior finishing works have commenced, along with a noticeable improvement in general site organization.
Expected next milestones
Completion of interior finishing works (electrical and plumbing), commencement of roof waterproofing, and intensification of exterior fencing works.