Miskan Al Sadan
24 Sept 2026

Al-Sadan

71%Overall▲ +4% · vs previous visit

Main video

Engineering Report

The current site visit shows significant progress in both exterior and interior finishing works, with steady momentum on site development and perimeter fencing, while the structural framework and foundations are now fully complete.
Detected changes
Finishing Works33%

Significant progress in plastering and exterior painting for select units, with ongoing internal electrical and mechanical installations.

Site Development and Fencing

Continued site grading and preparation of exterior fencing for the residential units.

Progress reading

The images reflect a 4% increase in finishing works and a 6% increase in fencing, which aligns with visual observations of accelerated plastering, exterior finishing, and site preparation around the units.

vs previous visit

Compared to the previous visit, the images show an increase in the number of units where exterior finishing works have commenced, along with a noticeable improvement in general site organization.

Expected next milestones

Completion of interior finishing works (electrical and plumbing), commencement of roof waterproofing, and intensification of exterior fencing works.

Progress

0%OverallAverage item progress
2/4 completeavg ▲ +3%
Finishing Works▲ +4%
0%
Fences and Courtyards▲ +6%
0%