Detected changes
The concrete structure for all residential units on-site has been completed.
Interior finishing works (plastering and MEP installations) have commenced in select units, with some units now featuring a base coat of paint.
Grading and paving works for roads and pathways between residential units are currently underway.
Progress reading
The reported completion rates (71% total) align with the visual status, as the structural framework is fully finished, while current efforts are concentrated on finishing works, which remain in their initial stages (30%), explaining the stability of the percentages compared to the previous visit.
vs previous visit
There are no significant tangible differences in completion percentages between the current and previous visits, as work has continued within the same scopes without major leaps in progress.
Expected next milestones
Intensification of interior finishing works, commencement of roof waterproofing, and the start of paving and site landscaping works.