Miskan Al Ghuroob
19 Aug 2026

Al-Ghuroob

71%Overall▲ +4% · vs previous visit

Main video

Engineering Report

The Maskan Al-Ghurub project was visited on August 19, 2026, with an overall completion rate of 71%. The project shows stability in progress compared to the previous visit, with the structural framework, foundations, and initial site works fully completed. Current efforts are focused on the interior and exterior finishing stages for a large number of residential units.
Detected changes
Structural Framework100%

Completion of all concrete and masonry works for all residential blocks by 100%, with units appearing in their final architectural massing.

Finishing Works90%

Continuation of external plastering and primary painting for some units, with others in advanced stages of interior finishing (installation of suspended ceilings and internal plastering).

General Site and Fencing85%

Demarcation of internal road paths and commencement of sub-grade preparation, with ongoing work on residential unit fencing and courtyards at varying completion rates.

Exterior Facades95%

Appearance of external paint samples on some villas, while most units remain in the cement plastering or exposed brick stage.

Progress reading

The visual evidence aligns with the reported completion rates; the full completion of the structural framework (100%) is clearly visible across the site. The stability of the finishing works at 30% and boundary walls at 19% indicates that recent work has focused on interior installations or tasks that did not significantly increase the overall visual completion percentage.

vs previous visit

Compared to the previous site visit photos (July 2026), the pace of work remains stable with slight progress in internal road grading and general site clearing, while the main building blocks remain unchanged as the structural work was previously completed.

Expected next milestones

Commencement of final road asphalt works, intensification of exterior painting, and installation of windows and doors for the residential units.

Progress

0%OverallAverage item progress
3/5 complete
Finishing Works
0%
Fences and Yards
0%
Structural Framework
0%
Foundations
0%
Excavation and Backfillingnew