Miskan Al Ghuroob
19 Aug 2026

Al-Ghuroob

71%Overall▲ +4% · vs previous visit

Main video

Engineering Report

The images show ongoing progress at the Maskan Al-Ghoroub project, with the structural framework for all residential units now complete. Current efforts are focused on interior and exterior finishing works and site preparation.
Detected changes
Structural Framework100%

The concrete structure for all residential units on-site has been completed.

Finishing Works30%

Interior finishing works (plastering and MEP installations) have commenced in select units, with some units now featuring a base coat of paint.

Site Development

Grading and paving works for roads and pathways between residential units are currently underway.

Progress reading

The reported completion rates (71% total) align with the visual status, as the structural framework is fully finished, while current efforts are concentrated on finishing works, which remain in their initial stages (30%), explaining the stability of the percentages compared to the previous visit.

vs previous visit

There are no significant tangible differences in completion percentages between the current and previous visits, as work has continued within the same scopes without major leaps in progress.

Expected next milestones

Intensification of interior finishing works, commencement of roof waterproofing, and the start of paving and site landscaping works.

Progress

0%OverallAverage item progress
3/5 complete
Finishing Works
0%
Fences and Yards
0%
Structural Framework
0%
Foundations
0%
Excavation and Backfillingnew
0%

Site (360)

3D

General Site Plan

Drone Shots

Models

M1

M2

M4

M5