Miskan Al Ghuroob
19 May 2026

Al-Ghuroob

62%Overall▲ +4% · vs previous visit

Main video

Engineering Report

The current site visit shows significant progress in interior and exterior finishing works for the residential complexes, with infrastructure and fencing works ongoing, while structural frameworks are now fully complete.
Detected changes
Finishing Works23%

Significant progress in plastering, initial painting, and electrical and plumbing installations within the residential units.

Site Development and Fencing

Ongoing paving of internal roads and development of the perimeter fencing surrounding the residential units.

Structural Framework100%

Completion of all concrete structures for the residential units, with no new structural changes.

Progress reading

The images reflect a 3% increase in finishing works, consistent with the progress in plastering and interior finishes observed in images 16-20. Additionally, the 3% increase in fencing and courtyard works is clearly evident in the improved state of the site and road paving.

vs previous visit

Compared to the previous visit, the current images show progress in interior finishing and landscaping, while the structural work remains fully complete.

Expected next milestones

Completion of final finishing works (painting, flooring, and electrical installations) and the commencement of exterior landscaping and planting.

Progress

0%OverallAverage item progress
2/4 completeavg ▲ +2%
Finishing Works▲ +3%
0%
Fences and Yards▲ +3%
0%
Structural Framework
0%
Foundations
0%

Site (360)

3D View

General Site Plan

Drone Photos

Models

M1

M2

M4