Engineering Report
Detected changes
Completion of initial asphalt works for the road network surrounding the residential units and demarcation of sidewalks.
Continuation of concrete pouring for slabs and columns across several units, with visible progress in masonry work using cement blocks.
Organization of the staging area and temporary offices, with an increased pace of equipment movement (concrete pumps and transport trucks).
Progress reading
Although the recorded percentages indicate 0%, the photos clearly demonstrate substantial completion of the structural framework (skeleton) and tangible development in general site works and paving. This necessitates an update to the completion percentages to reflect the actual reality shown in the images.
vs previous visit
Compared to the previous visit, we observe a transition from dirt roads to fully paved roads, an increase in the number of units with completed structural frameworks, and improved overall site organization and material distribution.
Expected next milestones
Commencement of external plastering works, installation of preliminary mechanical and electrical systems, and completion of the units' perimeter walls.