Engineering Report
Detected changes
Significant progress in plastering, initial painting, and electrical and plumbing installations within the residential units.
Ongoing paving of internal roads and development of the perimeter fencing surrounding the residential units.
Completion of all concrete structures for the residential units, with no new structural changes.
Progress reading
The images reflect a 3% increase in finishing works, consistent with the progress in plastering and interior finishes observed in images 16-20. Additionally, the 3% increase in fencing and courtyard works is clearly evident in the improved state of the site and road paving.
vs previous visit
Compared to the previous visit, the current images show progress in interior finishing and landscaping, while the structural work remains fully complete.
Expected next milestones
Completion of final finishing works (painting, flooring, and electrical installations) and the commencement of exterior landscaping and planting.