Engineering Report
Detected changes
Completion of all concrete works for all villas in the project by 100%, with structures clearly visible in aerial photographs.
Continuation of internal plastering and installation of gypsum ceiling panels in some units, with initial electrical wiring visible.
Commencement of construction for external boundary walls between residential units using cement blocks, and installation of some gates and entrances.
Execution of external plastering for facades and leveling of internal roads between residential blocks in preparation for paving works.
Progress reading
The visual documentation aligns with the recorded increase in finishing works (+3%) and boundary walls (+4%), clearly showing the transition from the structural shell stage to the closing of openings, plastering, and construction of the perimeter walls.
vs previous visit
Compared to the June 2026 imagery, there is a noticeable increase in the number of units where boundary wall construction has commenced, progress in the leveling of internal project roads, and advancement in internal gypsum ceiling works.
Expected next milestones
Completion of external plastering works, commencement of window and door installations, and initiation of final paving for internal roads.