Miskan Al Ghuroob
16 Jun 2026

Al-Ghuroob

65%Overall▲ +3% · vs previous visit

Main video

Engineering Report

Significant progress has been achieved at the Maskan Al-Ghurub project, with overall completion reaching 65%. The structural framework and foundations are 100% complete for all units, with focus shifting intensively toward interior and exterior finishing works, as well as the development of boundary walls and courtyard infrastructure.
Detected changes
Structural Framework100%

Final completion of concrete pouring for slabs and columns for all villas on-site.

Finishing Works95%

Commencement of external plastering works and application of waterproofing layers on several roofs.

Fences and Yards90%

Demarcation of external fence lines and start of foundation and partition wall construction between units.

Internal Roads95%

Grading of internal roads and application of initial asphalt layers in the project's pathways.

Progress reading

The images reflect the transition from the structural skeleton phase to the finishing stage; the completion of concrete structures (100%) is clearly visible, alongside the commencement of facade cladding and insulation works (27%). Privacy features are also beginning to take shape, with boundary wall construction progressing at 15%.

vs previous visit

Compared to the May 2026 visit, we observe a radical shift from active construction sites to completed structural blocks. All major structural openings have been closed, and heavy concrete equipment has begun to withdraw in favor of finishing and site landscaping machinery.

Expected next milestones

Completion of external plastering works, commencement of window and door installations, and intensification of work on mechanical and electrical system installations.

Progress

0%OverallAverage item progress
2/4 completeavg ▲ +2%
Finishing Works▲ +4%
0%
Fences and Yards▲ +5%
0%
Structural Frame
0%
Foundations
0%

Site (360)

3D

General Site Plan

Drone Photos

Models

M1

M2

M4

M5

ShareChat on WhatsApp