Al-Ghuroob
Main video
Engineering Report
Detected changes
Final completion of concrete pouring for slabs and columns for all villas on-site.
Commencement of external plastering works and application of waterproofing layers on several roofs.
Demarcation of external fence lines and start of foundation and partition wall construction between units.
Grading of internal roads and application of initial asphalt layers in the project's pathways.
Progress reading
The images reflect the transition from the structural skeleton phase to the finishing stage; the completion of concrete structures (100%) is clearly visible, alongside the commencement of facade cladding and insulation works (27%). Privacy features are also beginning to take shape, with boundary wall construction progressing at 15%.
vs previous visit
Compared to the May 2026 visit, we observe a radical shift from active construction sites to completed structural blocks. All major structural openings have been closed, and heavy concrete equipment has begun to withdraw in favor of finishing and site landscaping machinery.
Expected next milestones
Completion of external plastering works, commencement of window and door installations, and intensification of work on mechanical and electrical system installations.