Al-Ghuroob
Main video
Engineering Report
Detected changes
Concrete structures for all residential units are complete, with roof waterproofing works currently underway.
Progress is being made on exterior plastering, window frame installation, and the preparation of residential unit entrances.
Internal road paving continues, alongside the preparation of boundary fencing and exterior courtyards for the units.
Progress reading
The photos confirm the reported completion percentages, with the structural framework fully finished at 100%. Field operations are currently focused on finishing works (27%) and the development of boundary walls and courtyards (15%), which accounts for the slight increase in these figures compared to the previous visit.
vs previous visit
Compared to the previous visit, the site layout shows better organization of internal road networks, with a clear increase in the pace of exterior finishing works for the units, as the facades appear more complete than in previous images.
Expected next milestones
Completion of roof waterproofing, commencement of final facade finishing works, and intensification of internal road paving and site landscaping.