Miskan Al Ghuroob
16 Jun 2026

Al-Ghuroob

65%Overall▲ +3% · vs previous visit

Main video

Engineering Report

The current site visit shows significant progress in both exterior and interior finishing works for the residential units, alongside ongoing development of the site's general infrastructure and boundary walls, while all structural concrete works have been completed.
Detected changes
Structural Framework100%

Concrete structures for all residential units are complete, with roof waterproofing works currently underway.

Finishing Works27%

Progress is being made on exterior plastering, window frame installation, and the preparation of residential unit entrances.

Site Development and Fencing

Internal road paving continues, alongside the preparation of boundary fencing and exterior courtyards for the units.

Progress reading

The photos confirm the reported completion percentages, with the structural framework fully finished at 100%. Field operations are currently focused on finishing works (27%) and the development of boundary walls and courtyards (15%), which accounts for the slight increase in these figures compared to the previous visit.

vs previous visit

Compared to the previous visit, the site layout shows better organization of internal road networks, with a clear increase in the pace of exterior finishing works for the units, as the facades appear more complete than in previous images.

Expected next milestones

Completion of roof waterproofing, commencement of final facade finishing works, and intensification of internal road paving and site landscaping.

Progress

0%OverallAverage item progress
2/4 completeavg ▲ +2%
Finishing Works▲ +4%
0%
Fences and Yards▲ +5%
0%
Structural Frame
0%
Foundations
0%

Site (360)

3D

General Site Plan

Drone Photos

Models

M1

M2

M4

M5

ShareChat on WhatsApp