Detected changes
The images show interior plastering, window frame installation, and electrical and mechanical (plumbing) rough-ins within the residential units.
The concrete structure of the residential units is fully complete, with no significant structural changes compared to the previous visit.
Site landscaping works are ongoing, with incremental progress made on the perimeter courtyard fencing.
Progress reading
The 6% progress in finishing works (from 16% to 22%) reflects the notable activity in plastering and interior installations shown in the photos, while the stable percentages for the structural framework and foundations indicate that these phases were completed during previous visits.
vs previous visit
Compared to the previous visit, there is a clear shift in focus from structural work to interior finishing, while work on the site perimeter and fencing continues at a steady, albeit minor, pace.
Expected next milestones
Completion of painting and flooring installation, with the commencement of final exterior facade finishes and site landscaping.