Miskan Al Asala
20 Sept 2026

Al-Asalah

72%Overall▲ +3% · vs previous visit

Main video

Engineering Report

The current site visit shows significant progress in interior finishing works for residential units, with complete stability in the structural framework and foundations, alongside ongoing work on the general site and perimeter fencing.
Detected changes
Interior Finishing Works95%

The images show interior plastering, window frame installation, and electrical and mechanical (plumbing) rough-ins within the residential units.

Structural Framework100%

The concrete structure of the residential units is fully complete, with no significant structural changes compared to the previous visit.

Site Development and Fencing90%

Site landscaping works are ongoing, with incremental progress made on the perimeter courtyard fencing.

Progress reading

The 6% progress in finishing works (from 16% to 22%) reflects the notable activity in plastering and interior installations shown in the photos, while the stable percentages for the structural framework and foundations indicate that these phases were completed during previous visits.

vs previous visit

Compared to the previous visit, there is a clear shift in focus from structural work to interior finishing, while work on the site perimeter and fencing continues at a steady, albeit minor, pace.

Expected next milestones

Completion of painting and flooring installation, with the commencement of final exterior facade finishes and site landscaping.

Progress

0%OverallAverage item progress
0/4 completeavg ▲ +2%
Finishing Works▲ +6%
0%
Fences and Courtyards▲ +1%
0%
Structural Framework
0%
Foundations
0%

Drone Footage

Zone 1

360

Zone 2

360

Zone 3

360

Models

Model R1

Model R2

Model R3

360