Miskan Al Sadan
16 May 2026

Al-Sadan

57%Overall▲ +2% · vs previous visit

Main video

Engineering Report

Significant progress has been made on the Maskan Al-Sadan project, with overall completion reaching 57%. The structural framework and foundations are 100% complete, while interior and exterior finishing works continue to ramp up, and the formation of boundary walls and courtyards is becoming clearly visible across several sectors.
Detected changes
Structural Framework and Buildings100%

Completion of all concrete elements for the residential villas, with ongoing masonry work for internal and external block partitions and preparation of architectural openings.

Insulation and Roofing Works95%

Application of waterproofing (blue membrane) on the roofs of numerous residential units to ensure protection prior to the completion of finishing layers.

External Facades and Finishes90%

Commencement of external plastering and scaffolding installation for several blocks, with some units reaching advanced stages of white base-coat painting.

Fencing and Site Development85%

Progress in the construction of boundary walls between units, alongside ongoing leveling of internal roads and infrastructure preparation.

Progress reading

The visual progress aligns with the reported completion rates; the 100% completion of the concrete structure reflects the overall site status, while the commencement of plastering, insulation, and primary painting explains the 18% finishing progress. The increase in boundary wall construction (from 9% to 14%) is clearly evident in the defined courtyard paths between the villas.

vs previous visit

Compared to the previous site visit photos, the project has progressed from the structural casting phase to the building enclosure phase, including insulation and plastering. Additionally, most large construction cranes have been removed and replaced with finishing equipment and ground leveling machinery.

Expected next milestones

Completion of external plastering works, commencement of window and door installations, and intensification of internal electrical and mechanical piping works.

Progress

0%OverallAverage item progress
2/4 completeavg ▲ +30%
Finishing Works▲ +2%
0%
Fences and Courtyards▲ +5%
0%
Structural Frameworknew
0%
Foundations▲ +84%
0%