Miskan Al Sadan
16 May 2026

Al-Sadan

57%Overall▲ +2% · vs previous visit

Main video

Engineering Report

The project has seen significant progress in finishing works and site development, with the structural framework and foundations fully completed. Current efforts are focused on finalizing roof waterproofing and interior and exterior finishing for the residential units.
Detected changes
Structural Framework100%

The structural framework for all residential units is 100% complete.

Finishing Works18%

Waterproofing of roofs (blue membrane) has commenced, alongside electrical and plumbing installations in select units.

Site Development and Fencing

Progress is underway on boundary walls and external courtyards, with site preparation for pathways and areas surrounding the units.

Progress reading

The images align with the reported completion percentages; the structural concrete framework is clearly finished, while site photos confirm the commencement of roof waterproofing, which accounts for the 2% increase in finishing progress.

vs previous visit

Compared to the previous visit, the entire structural framework and foundations have been completed, with a notable increase in fencing and courtyard works (+5%), and the initial stages of roof finishing are now visible.

Expected next milestones

Completion of waterproofing for all roofs, commencement of plastering and exterior painting, and intensification of site development and landscaping works.

Progress

0%OverallAverage item progress
2/4 completeavg ▲ +30%
Finishing Works▲ +2%
0%
Fences and Courtyards▲ +5%
0%
Structural Frameworknew
0%
Foundations▲ +84%
0%