Miskan Al Sadan
12 Jul 2026

Al-Sadan

63%Overall▲ +2% · vs previous visit

Main video

Engineering Report

Significant progress has been achieved in the Maskan Al-Sadan project, with an overall completion rate of 63%. Recent work has focused on interior and exterior building finishes and fencing, while the structural framework and foundations for all units have reached 100% completion.
Detected changes
Finishing Works95%

Continuation of external and internal plastering works, alongside the commencement of electrical and mechanical network installations within residential units and roof preparation.

Fences and Courtyards90%

Progress in constructing residential unit fences using cement blocks and defining villa entrances, with ongoing soil leveling works for the courtyards.

General Site and Infrastructure95%

Clear definition of the internal road network between residential blocks, with continued backfilling, leveling, and preparation of the project's main pathways.

Progress reading

The visual evidence aligns with the recorded increase in finishing works (+3%) and fencing (+3%). Aerial and interior photographs show the transition from the raw concrete structural phase to wall cladding and the installation of essential utilities.

vs previous visit

Compared to the June visit, there is a noticeable increase in the number of villas with completed exterior plastering, an accelerated pace in the construction of boundary walls between units, and improved organization of the site's internal road networks.

Expected next milestones

Completion of exterior plastering for all blocks, commencement of primary painting works, and installation of final electrical systems.

Progress

0%OverallAverage item progress
2/4 completeavg ▲ +2%
Finishing Works▲ +3%
0%
Fences and Yards▲ +3%
0%
Structural Framework
0%
Foundations
0%

Site (360)

3D View

Master Plan

Drone Shots

Models