Al-Sadan
Main video
Engineering Report
Detected changes
Continuation of external and internal plastering works, along with the commencement of utility installations (electricity and plumbing) and the distribution of blocks within the units.
Progress in the application of primer coats for the external facades of several residential blocks, with units appearing in an initial white finish.
Execution of construction for boundary walls between residential units using cement blocks, and preparation of the entrances.
Continuation of earthwork leveling for internal roads and preparation of infrastructure pathways, with heavy machinery present on-site.
Progress reading
The visual evidence aligns with the recorded increase in finishing works (+3%), clearly showing the transition from raw concrete structures to the exterior cladding and interior partitioning phases. The images also support the increase in perimeter wall completion (+3%) by documenting the construction of dividing walls in the rear and side corridors of the units.
vs previous visit
Compared to the previous visit, an expansion in the scope of units entering the external plastering phase was observed, along with an increase in the quantities of staged materials (blocks and cables) on-site, and the completion of casting for several decorative elements on the villa rooftops.
Expected next milestones
Completion of external plastering works, commencement of window and door installations, and ongoing progress on mechanical and electrical system installations.