Al-Sadan
Main video
Engineering Report
Detected changes
Continuation of external and internal plastering works, alongside the commencement of electrical and mechanical network installations within residential units and roof preparation.
Progress in constructing residential unit fences using cement blocks and defining villa entrances, with ongoing soil leveling works for the courtyards.
Clear definition of the internal road network between residential blocks, with continued backfilling, leveling, and preparation of the project's main pathways.
Progress reading
The visual evidence aligns with the recorded increase in finishing works (+3%) and fencing (+3%). Aerial and interior photographs show the transition from the raw concrete structural phase to wall cladding and the installation of essential utilities.
vs previous visit
Compared to the June visit, there is a noticeable increase in the number of villas with completed exterior plastering, an accelerated pace in the construction of boundary walls between units, and improved organization of the site's internal road networks.
Expected next milestones
Completion of exterior plastering for all blocks, commencement of primary painting works, and installation of final electrical systems.